Creative Contractors recently completed a 27,350-square-foot renovation of the Natatorium at the Long Center in Clearwater. A community fixture since 1990, the facility is home to an Olympic-sized indoor pool and serves swimmers and families from throughout the region.
The project included replacement of the natatorium’s building envelope, a new roof, and a rooftop solar array featuring 401 panels with a total capacity of 429 kW. A new HVAC system was also installed to address heat and humidity within the pool area.
Creative also replaced pool mechanical room equipment and installed new perimeter gutter drains and a deck coating around the lap pool.
These improvements enhance the durability and comfort of the facility as it continues to support swimming, recreation, and water safety education for the community.
Architect: WJ Architects
Owner: City of Clearwater
Contract: $14,500,000
Completed: July 2026