October 23, 2023
Initial rendering for project.
October 23, 2023
Initial Site Photo
November 30, 2024
-Installed sleeves, paving and curbs.
-Began site grading.
-Continued with fiber cement board.
-Completed curtainwall installation.
-Completed framing and drywall.
-Painting was ongoing.
-Started millwork install.
-Started floor prep/moisture mitigation.
-Ceiling grid install was ongoing.
-MEP trim-out was underway.